The Center for Public Integrity offered the article below that challenges the current U.S. Nuclear Industry public relations campaign.
Events Get Ahead of the Regulators
Events Get Ahead of the Regulators
Earthquakes can occur in all sorts of locales. In January 1986, a late-morning quake measuring 4.96 on the Richter scale was blamed for cracks in the Perry Nuclear Power Plant on Lake Erie near Cleveland. At first, people thought it wasn’t a quake; speculation focused on an explosion somehow related to the Challenger space shuttle disaster or an attack on New York City. The newly licensed plant’s reactor was to be fueled for the first time the next day. Officials and the public were caught by surprise; few suspected Northeastern Ohio was in an active seismic zone. But it is. Experts determined that the quake’s epicenter was 11 miles from the plant, which has been dogged by controversy ever since.
A previously unknown fault line also runs near the Indian Point plant, 24 miles north of New York City. Indian Point’s two units are up for relicensing by the NRC in 2013 and 2015, respectively, and a fierce battle is expected. New York Gov. Andrew Cuomo, while campaigning last year, called for Indian Point to be closed. Now he has ordered a safety review of the plant. In a 2008 paper, four researchers from Columbia University reported that “Indian Point is situated at the intersection of the two most striking linear features marking the seismicity and also in the midst of a large population that is at risk in case of an accident at the plants.” Indian Point’s two reactors, the researchers noted, “are located closer to more people at any given distance than any other similar facilities in the United States.”
The plant’s operator, Entergy Corp., issued a statement saying all its nuclear plants “were designed and built to withstand the effects of natural disasters, including earthquakes and catastrophic flooding. The NRC requires that safety-significant structures, systems and components be designed to take into account the most severe natural phenomena historically reported for each site and surrounding area.”
[Entergy is the company that operates the Plymouth, MA nuclear power plant.]
The article is worth reading in its entirety:
Regulators aware for years of understated seismic risks to nuclear plants
Despite six years of study, industry collaboration, and a missed deadline, no decision on reactor fixes
By Jim Morris and Bill Sloat
Nearly six years before an earthquake ravaged Japan’s Fukushima Daiichi nuclear power plant, U.S. regulators came to a sobering realization: seismic risks to nuclear plants in the eastern two-thirds of the country were greater than had been suspected, and engineers might have to rethink reactor designs.
For more information on each nuclear reactor in our map, download the list.
Thus began a little-noticed risk assessment process with far-reaching implications despite its innocuous-sounding name: Generic Issue 199. The process, which was supposed to have been finished nearly a year ago, is still under way. It is unclear when it will be completed.GI-199, as it is known, was triggered by new geophysical data and computer models showing that, as the Nuclear Regulatory Commission put it in an August 2010 summary document, “estimates of the potential for earthquake hazards for some nuclear power plants in the Central and Eastern United States may be larger than previous estimates.”
Data from the U.S. Geological Survey and other sources suggest, for example, that “the rate of earthquake occurrence … is greater than previously recognized” in eastern Tennessee and areas including Charleston, S.C., and New Madrid, Mo., according to the NRC document. There are 11 reactors in Tennessee, South Carolina and Missouri.